Monday, October 15, 2018

Garage Footing

Garage footing poured and block foundation completed with tie straps.

Tuesday, October 9, 2018

Brick Window Work

Old windows bricked in and new window cut out and installed.



Monday, October 8, 2018

Fence and Step Install

old iron railing removed and new wood rail and steps installed with aluminum spindles and gate.


Sunday, September 23, 2018

Saturday, September 22, 2018

Stair Railing Project

Old railing removed and new square posts and square top rail installed with horizontal spindles.




Friday, September 21, 2018

Chimney Build

Chimney tore down about 10 coarses. reused good bricks and installed new for the top. Installed cap with wash.

Thursday, September 20, 2018

Garage Build

garage build. New footing slab and driveway, electrical, doors, siding and roof. Brick facing installed on each side of door.




Friday, August 31, 2018

Friday, August 17, 2018

Composite deck with Water Features

Composite deck built overhanging pond. Pond, river, garden and waterfalls. Put's Pond and Garden installed the water and garden features.